Check Performance Data - Testing guide: add the revised results (the "16 to 19 Feb" and "16 to 19 Mar" windows)

This guide tests the February step of the 16-19 results enquiry. An admin adds the two revised results files (16to19_INC_REV and 16to19_NONINC_REV) to a results enquiry that already has an October and a November release. The revised files replace the included, non-included and both late results files, so the admin also retires those four slots. The last part tests the March step: the included revised with retention file (16to19_INC_REV_RET) replaces included revised.

What the seed gives you

The dev seed makes a window for each step. All have the same exercises, slots and dates.

  • "16 to 19 Nov" (DevDataSeeder.Post16NovemberCheckingWindowId, 3b1d7c52-6e0a-4f8b-9c21-5a4e8d7f1b63) is the state before the February step: the October files and late results 2 are validated. The results enquiry has two releases, October and November (live). Use it to add the revised files by hand.
  • "16 to 19 Feb" (DevDataSeeder.Post16FebruaryCheckingWindowId, 9e2a4c71-3b5d-4f60-8a17-c4d2e6f80b95) is the state after the February step (SeedPost16FebruarySamples): the revised files are validated and the four files they replace are retired. It has three releases. It is also the state before the March step.
  • "16 to 19 Mar" (DevDataSeeder.Post16MarchCheckingWindowId, 5c8f1e26-7a94-4d3b-b06e-2f9d4a1c7e58) is the state after the March step (SeedPost16MarchSamples): included revised with retention is validated and included revised is retired. It has four releases.
Exercise Slot File Schema Nov Feb Mar
Pupil data checking Students: included included.csv students-included_schema.json Validated Validated Validated
Pupil data checking Students: non-included nonincluded.csv students-non-included_schema.json Validated Validated Validated
Results enquiry Included 16to19_INC.csv results-included_schema.json Live Retired Retired
Results enquiry Non-included 16to19_NONINC.csv results-non-included_schema.json Live Retired Retired
Results enquiry Late results 1 16to19_LR1.csv results-late_schema.json Live Retired Retired
Results enquiry Late results 2 16to19_LR2.csv results-late-2_schema.json Live Retired Retired
Results enquiry Included revised 16to19_INC_REV.csv results-included-revised_schema.json Not supplied Live Retired
Results enquiry Non-included revised 16to19_NONINC_REV.csv results-non-included-revised_schema.json Not supplied Live Live
Results enquiry Included revised with retention 16to19_INC_REV_RET.csv results-included-revised-retention_schema.json Not supplied Not supplied Live

The seed also writes the revised samples to the ingress storage account, container 16-to-19-feb:

File Schema (upload from your machine) Rows
results/16to19_INC_REV.csv results-included-revised_schema.json 62
results/16to19_NONINC_REV.csv results-non-included-revised_schema.json 33

The schemas are in src/DfE.CheckPerformanceData.Web/Data/Ingress/post16/. They have the same columns as results-included_schema.json and results-non-included_schema.json, but their own collection, download file and section, so each revised file is its own section on the Results tab.

What the revised files hold

The revised files hold one row for each result in the four earlier files (98 rows become 95). Where a late file amended a result, the revised file holds only the amended grade. A student is in the included revised file when the student is included, and in the non-included revised file when not.

CYPMD ID Student Qualification November release Revised
500001 Alice Smith GCSE English Language (60148366), S2024 6 (Late results 1) and 7 (Late results 2) 7
500003 Charlie Smith GCSE Mathematics (60146084), S2024 2 (Included) and 3 (Late results 2) 3
500002 Bob Smith BTEC Sport (60172186), S2024 M (Included) and D (Late results 1) D
500001 Alice Smith GCE A Level Art and Design (60149589), S2024 A (Included) B — changed only in the revised file
500005 Edward Smith OCR FSMQ Additional Maths (10025480), S2024 B (Late results 2) B
500202 Bob Johnson (non-included) BTEC Sport (60172186), S2024 M (Late results 2) M, in the non-included revised file

Alice Smith's two GCSE Mathematics results (S2023 and S2024) stay two rows: the sessions differ.

Before you start

  1. Start the stack and seed:

    docker compose --profile web --profile database --profile storage up -d --build
    

    Or run the web app with dotnet run --project src/DfE.CheckPerformanceData.Web --launch-profile http.

  2. If the database already has windows from an earlier seed, use Reset seed data on the admin danger zone page. The seed deletes and makes all dev windows again.

  3. Sign in as an admin: /dev/impersonate/admin. For school pages, use /dev/impersonate/editor. Do not open /LandingPage while you impersonate.

Tests 1 to 4 and 7 add the revised files by hand on the November window. The February window already has the result of those steps: use it for Tests 5 and 6 if you do not want to do them.

Test 1: the November window is correct

  1. As an admin, open /admin/windows/summary/3b1d7c52-6e0a-4f8b-9c21-5a4e8d7f1b63.
  2. Make sure that both exercises show the Validated tag.
  3. In the Results enquiry data files table, make sure that Included, Non-included, Late results 1 and Late results 2 show their file and schema names, and that Included revised and Non-included revised show Not supplied and (optional).
  4. Open the Results enquiry edit page, Data tab. Make sure that the Status column shows Live for Included, Non-included, Late results 1 and Late results 2, and Not supplied for the three revised slots (Included revised, Non-included revised, Included revised with retention).
  5. In Data releases, make sure that there are two releases and that the second (November) is live.
  6. As an editor, open /CheckYourPupilData/3b1d7c52-6e0a-4f8b-9c21-5a4e8d7f1b63.
  7. Open the Results tab. Make sure that it shows the Included, Non-included, Late results and Late results 2 sections.

Test 2: add the revised files

Add the files before you retire the old slots. Validate data is not available while no slot in use holds a file.

  1. As an admin, open the window summary. Choose Edit on the Results enquiry, then the Data tab.
  2. On the Included revised row, choose Choose CSV. Open the 16-to-19-feb container, then results/. Choose 16to19_INC_REV.csv.
  3. On the same row, choose Choose schema. Upload results-included-revised_schema.json.
  4. On the Non-included revised row, choose 16to19_NONINC_REV.csv and upload results-non-included-revised_schema.json.
  5. Make sure that both revised rows show Not validated. Schools do not see them yet.
  6. Make sure that the validation line reads Files have changed since the last validation.

Test 3: retire the four replaced files

  1. On the Included row, in the In use column, choose Retire.
  2. Make sure that the confirmation page says that the next validation makes a release without the file, and that schools keep the live release until then. Choose Retire data file.
  3. Make sure that the Included row now shows the grey Retired tag, where it showed Live, and Put back in use.
  4. Do the same for Non-included, Late results 1 and Late results 2.
  5. Make sure that each of the four rows says Retired under its name, where it said Required or Optional before.
  6. As an editor, open the Results tab. Make sure that it still shows the November sections. Retiring does not change the live release.
  7. As an admin, open the window summary. Make sure that the Results enquiry data files table shows only Included revised and Non-included revised. The summary does not list retired slots.
  8. Make sure that Pupil data checking is still Validated.

Test 4: validate the February release

  1. On the Results enquiry Data tab, choose Validate data. Wait for the run to complete without errors.
  2. Make sure that the validation line reads Up to date.
  3. Make sure that both revised rows now show Live, the four retired rows still show Retired, and Included revised with retention still shows Not supplied.
  4. In Data releases, make sure that there is a third release and that it is live. The October and November releases are still in the list. The February window shows the same.

Test 5: schools see only the revised results

Do this on the February window, or on the November window after Test 4.

  1. As an editor, open /CheckYourPupilData/9e2a4c71-3b5d-4f60-8a17-c4d2e6f80b95.
  2. Open the Results tab. Make sure that it shows Results included revised (62 rows) and Results non-included revised (33 rows), and no Included, Non-included, Late results or Late results 2 section.
  3. Start the results enquiry and choose Incorrect grade.
  4. Make sure that the late results guidance page does not show. The journey goes straight to "Does the incorrect grade affect the whole cohort?".
  5. Search for Alice Smith. Choose her. Make sure that:
    • GCSE English Language shows once, grade 7, File: Included revised.
    • GCE A Level Art and Design shows grade B.
    • GCSE Mathematics shows twice, S2023 (grade 4) and S2024 (grade 5).
  6. Go back and choose Charlie Smith. Make sure that GCSE Mathematics shows once, grade 3.
  7. Choose Bob Smith. Make sure that BTEC Sport shows once, grade D.
  8. Choose Edward Smith. Make sure that he is still in the suggestions, with the FSMQ Additional Maths result, File: Included revised.
  9. Search for Bob Johnson (non-included). Make sure that his BTEC Sport result shows File: Non-included revised.

Test 6: go back to the November release (optional)

  1. As an admin, on the Results enquiry edit page, in Data releases, choose Make live on the November release.
  2. As an editor, make sure that the Results tab shows the four November sections again, and that Alice Smith's English Language shows twice (grades 6 and 7).
  3. Make the February release live again.

Test 7: put a slot back in use (optional)

  1. As an admin, on the Data tab, choose Put back in use on Late results 2 and confirm.
  2. Make sure that Late results 2 shows Not validated: the live February release did not read it.
  3. Make sure that the validation line reads Files have changed since the last validation.
  4. Retire Late results 2 again. Do not validate with it back in use: its rows would show beside the revised rows that already hold them.

Test 8: add included revised with retention by hand (March)

Do this on the February window. The March window already has the result of these steps.

The seed writes the sample to the ingress storage account, container 16-to-19-mar:

File Schema (upload from your machine) Rows
results/16to19_INC_REV_RET.csv results-included-revised-retention_schema.json 62

The file holds the same rows as the included revised file, with one grade changed: Charlie Smith (500003), GCSE Mathematics (60146084), S2024, 3 → 4.

  1. As an admin, open /admin/windows/summary/9e2a4c71-3b5d-4f60-8a17-c4d2e6f80b95. Choose Edit on the Results enquiry, then the Data tab.
  2. On the Included revised with retention row, choose Choose CSV. Open the 16-to-19-mar container, then results/. Choose 16to19_INC_REV_RET.csv.
  3. On the same row, choose Choose schema. Upload results-included-revised-retention_schema.json.
  4. On the Included revised row, choose Retire and confirm.
  5. Choose Validate data. Wait for the run to complete without errors.
  6. Make sure that Included revised with retention and Non-included revised show Live, and the other five slots show Retired.
  7. In Data releases, make sure that there is a fourth release and that it is live.

Test 9: schools see the retention results (March)

Do this on the March window, or on the February window after Test 8.

  1. As an editor, open /CheckYourPupilData/5c8f1e26-7a94-4d3b-b06e-2f9d4a1c7e58.
  2. Open the Results tab. Make sure that it shows Results included revised with retention (62 rows) and Results non-included revised (33 rows), and no Results included revised section.
  3. Start the results enquiry and choose Incorrect grade.
  4. Choose Charlie Smith. Make sure that GCSE Mathematics shows once, grade 4, File: Included revised with retention.
  5. Search for Bob Johnson (non-included). Make sure that his BTEC Sport result still shows File: Non-included revised.
  6. As an admin, on the March window's Results enquiry edit page, choose Make live on the February release. Make sure that Charlie Smith's Maths grade is 3 again. Then make the March release live again.

Automated cover